What is the minimum obstacle clearance (MOC) required in the primary area of the initial approach segment for an instrument approach procedure?

Study for the ATPL Intensive Program Exam. Use multiple choice questions and flashcards, each with hints and explanations. Master your exam preparation and succeed!

The minimum obstacle clearance (MOC) required in the primary area of the initial approach segment for an instrument approach procedure is 300 meters (984 feet). This clearance is essential to ensure that aircraft can safely navigate during the initial phase of approach without the risk of colliding with any obstacles that may be present in that area. The regulations governing these standards are set to provide a buffer zone that accounts for potential inaccuracies in navigation and variations in aircraft performance.

The primary area of the initial approach segment typically extends from the point where the aircraft begins its approach to the point where it starts its final descent. Maintaining a minimum clearance of 300 meters ensures that the aircraft remains clear of obstacles while operating in the controlled environment of the initial approach. This clearance also reflects the safety margins considered necessary for flight operations as defined by aviation authority standards, ensuring safe and efficient transitions onto final approach and landing.

Other options represent higher clearance requirements that may apply to different segments or types of approaches, but for the specific phase in question, the established minimum requirement is indeed 300 meters.